How to arrange for a new sub contractor to start on a Monday

Added: Fri, 27 Jan 2017  

Your new sub contractor has a FS link which requires a start on Thursday afternoon.  Even with a Start Next Day switch you know he will arrive on the Monday - they always do. What to do? Crea...

Tracking Cross Chart Links

Added: Fri, 27 Jan 2017  

When your programme has multiple charts and you are linking between tasks then it is necessary to create a visible reference on each chart. To do this simply create a milestone under the top chart tas...

Basic rules of concurrency

Added: Fri, 27 Jan 2017  

Any relevant delay caused by the Employer will always entitle the Contractor to an EoT The Contractor will only get costs for the period where the Employer's Delay exceeds his own. The Employer ca...

Dealing with curing periods

Added: Fri, 27 Jan 2017  

There is a drying out period between pouring concrete and striking forms.  This is covered by a lead lag of the required duration BUT with a 24/7 calendar on it.  However if this lag ends in...

Coming Soon

Added: Sat, 10 Dec 2016  

Coming soon! Truly flexible online outsourcing for Construction Planning services. Follow us for regular updates on our launch on Twitter @temptaskCP. For further pre-launch information, please c...